webdev


Project Start Date: Tue 11/20/01
Project Finish Date: Fri 2/8/02

Top Level Tasks

ID
Task Name
DurationStartFinish% CompleteCostWork
1
1. Initiation (Inception) Phase
17 days?Tue 11/20/01Wed 12/12/013%$20,400.00208 hrs
19
Planning / Design (Elaboration) Phase
11 days?Wed 12/12/01Thu 12/27/010%$9,400.0096 hrs
36
Execution (Construction) Phase
15 days?Tue 12/25/01Mon 1/14/020%$22,600.00264 hrs
58
Close-out / Transition (Launch) Phase
59 days?Tue 11/20/01Fri 2/8/020%$17,440.00256 hrs