Project Start Date: Tue 11/20/01
Project Finish Date: Fri 2/8/02

Who Does What

Resources and Assignments
StartFinishWork
Client Sponsor
Wed 11/21/01Tue 12/11/0132 hrs
Review
Wed 11/21/01Wed 11/21/018 hrs
Storyboard use case scenario design
Thu 11/22/01Thu 11/22/018 hrs
Concept approved
Thu 11/22/01Thu 11/22/010 hrs
Client concept review
Tue 11/27/01Tue 11/27/018 hrs
Client acceptance
Wed 11/28/01Wed 11/28/010 hrs
Project Plan Management Reviews
Tue 12/11/01Tue 12/11/018 hrs
Own Creative Lead
Tue 11/27/01Thu 12/6/0156 hrs
Client concept review
Tue 11/27/01Tue 11/27/018 hrs
Creative Development
Thu 11/29/01Thu 12/6/0148 hrs
Developers
Fri 12/7/01Thu 12/27/0196 hrs
Functional Spec writing
Fri 12/7/01Mon 12/10/0116 hrs
Project Plan Management Reviews
Tue 12/11/01Tue 12/11/018 hrs
Begin Production Guide
Fri 12/14/01Fri 12/14/018 hrs
Create directory structure
Mon 12/17/01Mon 12/17/018 hrs
Production package received
Mon 12/17/01Mon 12/17/010 hrs
Obtain tight comps from Designer
Tue 12/18/01Tue 12/18/018 hrs
Add Spec info to Production Guide
Wed 12/19/01Wed 12/19/018 hrs
Create grid
Thu 12/20/01Thu 12/20/018 hrs
Cut graphics
Fri 12/21/01Fri 12/21/018 hrs
Create animations
Mon 12/24/01Mon 12/24/018 hrs
Handoff to coder
Mon 12/24/01Mon 12/24/010 hrs
Internal Production Review
Wed 12/26/01Wed 12/26/018 hrs
Final Production
Thu 12/27/01Thu 12/27/018 hrs
Handoff to testing
Thu 12/27/01Thu 12/27/010 hrs
Ops
Thu 12/13/01Fri 2/8/02160 hrs
Create staging Environment
Thu 12/13/01Thu 12/13/018 hrs
Install in production parallel environment
Tue 1/8/02Tue 1/8/028 hrs
Test and tune performance
Wed 1/9/02Wed 1/9/028 hrs
Obtain Performance baselines
Thu 1/10/02Thu 1/10/028 hrs
Performance report
Fri 1/11/02Fri 1/11/028 hrs
PreLaunch Decision Meeting
Mon 1/14/02Mon 1/14/028 hrs
Initial Operation and Maintenance
Tue 1/22/02Mon 2/4/0280 hrs
Review Initial Webtrends stats
Tue 2/5/02Tue 2/5/028 hrs
Post-implementation analysis
Wed 2/6/02Thu 2/7/0216 hrs
Post-implementation Review meeting
Fri 2/8/02Fri 2/8/028 hrs
Pmgr
Thu 11/29/01Mon 1/7/02136 hrs
Programming
Thu 11/29/01Thu 12/6/0148 hrs
Code HTML files
Tue 12/25/01Tue 12/25/018 hrs
Internal Production Review
Wed 12/26/01Wed 12/26/018 hrs
Programming
Fri 12/28/01Tue 1/1/0224 hrs
Lessons Learned Report
Fri 12/28/01Tue 1/1/0224 hrs
Functionality Bug fixes
Thu 1/3/02Mon 1/7/0224 hrs
CSR
Tue 11/20/01Mon 1/21/0216 hrs
Delivery/notification to customer
Mon 1/21/02Mon 1/21/028 hrs
User Training
Tue 11/20/01Tue 11/20/018 hrs
QA
Tue 12/25/01Mon 1/14/02144 hrs
Write QA Test Plan
Tue 12/25/01Tue 12/25/018 hrs
Create QA test suites
Wed 12/26/01Wed 12/26/018 hrs
Configure QA enviornment
Thu 12/27/01Thu 12/27/018 hrs
Customize bug database
Fri 12/28/01Fri 12/28/018 hrs
Usability Testing
Mon 12/31/01Wed 1/2/0224 hrs
Install in QA environment
Fri 12/28/01Fri 12/28/018 hrs
Identify, record, analyze functionality bugs
Fri 12/28/01Wed 1/2/0232 hrs
Functionality Test Signoff
Mon 1/7/02Mon 1/7/020 hrs
Functionality Test Report
Tue 1/8/02Tue 1/8/028 hrs
Scalability & Performance Tuning
Tue 1/8/02Mon 1/14/0240 hrs
Project Manager
Thu 11/22/01Fri 2/8/0272 hrs
Concept approved
Thu 11/22/01Thu 11/22/010 hrs
Risk Evaluation
Fri 11/23/01Mon 11/26/0116 hrs
Client acceptance
Wed 11/28/01Wed 11/28/010 hrs
Design Lockdown
Thu 12/6/01Thu 12/6/010 hrs
Project Plan Revisions
Wed 12/12/01Wed 12/12/018 hrs
Project Plan Approved!
Wed 12/12/01Wed 12/12/010 hrs
Receive package
Wed 12/12/01Wed 12/12/010 hrs
PreLaunch Decision Meeting
Mon 1/14/02Mon 1/14/028 hrs
Acquire and Test Training and Support Capabilities
Tue 1/15/02Thu 1/17/0224 hrs
Internal Announcement/Promotion
Fri 1/18/02Fri 1/18/028 hrs
Post-implementation Review meeting
Fri 2/8/02Fri 2/8/028 hrs
Sales
Tue 11/20/01Wed 11/28/0124 hrs
Define Project Strategy
Tue 11/20/01Tue 11/20/018 hrs
Review
Wed 11/21/01Wed 11/21/018 hrs
Finalize contract
Wed 11/28/01Wed 11/28/018 hrs
Mkt
Mon 1/21/02Mon 2/4/0288 hrs
External Announcement/Publicity
Mon 1/21/02Mon 2/4/0288 hrs