Project Start Date: Tue 11/20/01
Project Finish Date: Fri 2/8/02
Resources and Assignments | Start | Finish | Work |
---|---|---|---|
Client Sponsor | Wed 11/21/01 | Tue 12/11/01 | 32 hrs |
Review | Wed 11/21/01 | Wed 11/21/01 | 8 hrs |
Storyboard use case scenario design | Thu 11/22/01 | Thu 11/22/01 | 8 hrs |
Concept approved | Thu 11/22/01 | Thu 11/22/01 | 0 hrs |
Client concept review | Tue 11/27/01 | Tue 11/27/01 | 8 hrs |
Client acceptance | Wed 11/28/01 | Wed 11/28/01 | 0 hrs |
Project Plan Management Reviews | Tue 12/11/01 | Tue 12/11/01 | 8 hrs |
Own Creative Lead | Tue 11/27/01 | Thu 12/6/01 | 56 hrs |
Client concept review | Tue 11/27/01 | Tue 11/27/01 | 8 hrs |
Creative Development | Thu 11/29/01 | Thu 12/6/01 | 48 hrs |
Developers | Fri 12/7/01 | Thu 12/27/01 | 96 hrs |
Functional Spec writing | Fri 12/7/01 | Mon 12/10/01 | 16 hrs |
Project Plan Management Reviews | Tue 12/11/01 | Tue 12/11/01 | 8 hrs |
Begin Production Guide | Fri 12/14/01 | Fri 12/14/01 | 8 hrs |
Create directory structure | Mon 12/17/01 | Mon 12/17/01 | 8 hrs |
Production package received | Mon 12/17/01 | Mon 12/17/01 | 0 hrs |
Obtain tight comps from Designer | Tue 12/18/01 | Tue 12/18/01 | 8 hrs |
Add Spec info to Production Guide | Wed 12/19/01 | Wed 12/19/01 | 8 hrs |
Create grid | Thu 12/20/01 | Thu 12/20/01 | 8 hrs |
Cut graphics | Fri 12/21/01 | Fri 12/21/01 | 8 hrs |
Create animations | Mon 12/24/01 | Mon 12/24/01 | 8 hrs |
Handoff to coder | Mon 12/24/01 | Mon 12/24/01 | 0 hrs |
Internal Production Review | Wed 12/26/01 | Wed 12/26/01 | 8 hrs |
Final Production | Thu 12/27/01 | Thu 12/27/01 | 8 hrs |
Handoff to testing | Thu 12/27/01 | Thu 12/27/01 | 0 hrs |
Ops | Thu 12/13/01 | Fri 2/8/02 | 160 hrs |
Create staging Environment | Thu 12/13/01 | Thu 12/13/01 | 8 hrs |
Install in production parallel environment | Tue 1/8/02 | Tue 1/8/02 | 8 hrs |
Test and tune performance | Wed 1/9/02 | Wed 1/9/02 | 8 hrs |
Obtain Performance baselines | Thu 1/10/02 | Thu 1/10/02 | 8 hrs |
Performance report | Fri 1/11/02 | Fri 1/11/02 | 8 hrs |
PreLaunch Decision Meeting | Mon 1/14/02 | Mon 1/14/02 | 8 hrs |
Initial Operation and Maintenance | Tue 1/22/02 | Mon 2/4/02 | 80 hrs |
Review Initial Webtrends stats | Tue 2/5/02 | Tue 2/5/02 | 8 hrs |
Post-implementation analysis | Wed 2/6/02 | Thu 2/7/02 | 16 hrs |
Post-implementation Review meeting | Fri 2/8/02 | Fri 2/8/02 | 8 hrs |
Pmgr | Thu 11/29/01 | Mon 1/7/02 | 136 hrs |
Programming | Thu 11/29/01 | Thu 12/6/01 | 48 hrs |
Code HTML files | Tue 12/25/01 | Tue 12/25/01 | 8 hrs |
Internal Production Review | Wed 12/26/01 | Wed 12/26/01 | 8 hrs |
Programming | Fri 12/28/01 | Tue 1/1/02 | 24 hrs |
Lessons Learned Report | Fri 12/28/01 | Tue 1/1/02 | 24 hrs |
Functionality Bug fixes | Thu 1/3/02 | Mon 1/7/02 | 24 hrs |
CSR | Tue 11/20/01 | Mon 1/21/02 | 16 hrs |
Delivery/notification to customer | Mon 1/21/02 | Mon 1/21/02 | 8 hrs |
User Training | Tue 11/20/01 | Tue 11/20/01 | 8 hrs |
QA | Tue 12/25/01 | Mon 1/14/02 | 144 hrs |
Write QA Test Plan | Tue 12/25/01 | Tue 12/25/01 | 8 hrs |
Create QA test suites | Wed 12/26/01 | Wed 12/26/01 | 8 hrs |
Configure QA enviornment | Thu 12/27/01 | Thu 12/27/01 | 8 hrs |
Customize bug database | Fri 12/28/01 | Fri 12/28/01 | 8 hrs |
Usability Testing | Mon 12/31/01 | Wed 1/2/02 | 24 hrs |
Install in QA environment | Fri 12/28/01 | Fri 12/28/01 | 8 hrs |
Identify, record, analyze functionality bugs | Fri 12/28/01 | Wed 1/2/02 | 32 hrs |
Functionality Test Signoff | Mon 1/7/02 | Mon 1/7/02 | 0 hrs |
Functionality Test Report | Tue 1/8/02 | Tue 1/8/02 | 8 hrs |
Scalability & Performance Tuning | Tue 1/8/02 | Mon 1/14/02 | 40 hrs |
Project Manager | Thu 11/22/01 | Fri 2/8/02 | 72 hrs |
Concept approved | Thu 11/22/01 | Thu 11/22/01 | 0 hrs |
Risk Evaluation | Fri 11/23/01 | Mon 11/26/01 | 16 hrs |
Client acceptance | Wed 11/28/01 | Wed 11/28/01 | 0 hrs |
Design Lockdown | Thu 12/6/01 | Thu 12/6/01 | 0 hrs |
Project Plan Revisions | Wed 12/12/01 | Wed 12/12/01 | 8 hrs |
Project Plan Approved! | Wed 12/12/01 | Wed 12/12/01 | 0 hrs |
Receive package | Wed 12/12/01 | Wed 12/12/01 | 0 hrs |
PreLaunch Decision Meeting | Mon 1/14/02 | Mon 1/14/02 | 8 hrs |
Acquire and Test Training and Support Capabilities | Tue 1/15/02 | Thu 1/17/02 | 24 hrs |
Internal Announcement/Promotion | Fri 1/18/02 | Fri 1/18/02 | 8 hrs |
Post-implementation Review meeting | Fri 2/8/02 | Fri 2/8/02 | 8 hrs |
Sales | Tue 11/20/01 | Wed 11/28/01 | 24 hrs |
Define Project Strategy | Tue 11/20/01 | Tue 11/20/01 | 8 hrs |
Review | Wed 11/21/01 | Wed 11/21/01 | 8 hrs |
Finalize contract | Wed 11/28/01 | Wed 11/28/01 | 8 hrs |
Mkt | Mon 1/21/02 | Mon 2/4/02 | 88 hrs |
External Announcement/Publicity | Mon 1/21/02 | Mon 2/4/02 | 88 hrs |